Different inspections are required for each permit. Required inspections include:
Building
- Footing / Piers - Prior to pouring
- Foundation Wall - Prior to pouring and after reinforcing is placed
- Framing - Prior to installation of insulation and drywall
- Final - Prior to occupancy
Demolition
Plumbing
- Ground Rough - Basement
- Rough - Fixtures
- Final
Mechanical
- Rough inspections, when work is completed, and ready for inspection
Electrical
- T.O.P - Temporary electric on pole
- T.O.P - Temporary electric meter base on exterior of house
- Rough - Wiring
- Final
Final
- This is the overall inspection when all work is completed and occupancy or use is considered
Fence
Pool - Above Ground
- Electric - Licensed electrician required
Pool - In Ground
- Electric - Licensed electrician required
- Rough Plumbing - Licensed plumber required
- Final